The project consists of furnishing all material and constructing the following:
• Removal of the discharge piping associated with Washwater Pump #3 (WWP3) up to the
discharge tee.
• Installation of a new discharge isolation valve and discharge check valve;
• Reconstruction of the discharge piping and small diameter instrumentation piping;
• Removal of existing foot valve from WWP3 (Alternate No. 1), replacement of foot
valves at WWP2 and WWP3 suction piping (Alternate No. 2) including installation of
permanent pipe supports (both Alternates).
• All associated equipment, valves, piping, and mechanical work.
Including all necessary appurtenances, disinfection, and restoration.